Bond Project - September 19, 2025 Update

CHS - Athletics Entrance
CHS - Athletics Entrance
CHS - Athletic Corridor Vinyl In Progress
CHS - Athletic Corridor Vinyl In Progress
CHS - Trojan Hall of Fame
CHS - Trojan Hall of Fame
CHS - Auditorium Lobby Flooring in Progress
CHS - Auditorium Lobby Flooring in Progress

Current Activities & Tasks

• CHS – Punch List Repairs in progress.
• CHS – Auditorium Stage Lighting in progress.
• CHS – Auditorium Lobby Concrete in fill in progress.
• CHS – Athletic Area Paint Touch Ups in progress.
• CHS – Athletic Area Final Cleaning

Upcoming Activities & Tasks

CHS – Continue Punch List Repairs.
CHS – Continue Weight Room Flooring prep & install.