September Updates
Bond Project - September 19, 2025 Update
Current Activities & Tasks
• CHS – Punch List Repairs in progress.
• CHS – Auditorium Stage Lighting in progress.
• CHS – Auditorium Lobby Concrete in fill in progress.
• CHS – Athletic Area Paint Touch Ups in progress.
• CHS – Athletic Area Final Cleaning
Upcoming Activities & Tasks
• CHS – Continue Punch List Repairs.
• CHS – Continue Weight Room Flooring prep & install.
• CHS – Weight Room Equipment