Bond Project - October 17, 2025 Update

CHS - Auditorium Lobby Thin Brick in Progress
CHS - Auditorium Lobby Thin Brick in Progress
CHS - Auditorium Lobby Toilet Room Plumbing Fixtures in Progress
CHS - Auditorium Lobby Toilet Room Plumbing Fixtures in Progress
CHS - Auditorium Stage in Progress
CHS - Auditorium Stage in Progress
CHS - New Gymnasium Wall Pads
CHS - New Gymnasium Wall Pads

Current Activities & Tasks

  • CHS - Punch List Repairs in progress.
  • CHS - Auditorium Stage Lighting in progress.CHS - Auditorium Lobby Thin Brick in progress.
  • CHS - Auditorium Lobby Painting in progress.
  • CHS - Auditorium Lobby Plumbing in progress.
  • CHS - Cleaning Auditorium Stage to prep for floor install on Monday, 10/20

Upcoming Activities & Tasks

  • CHS - Continue Punch List Repairs.
  • CHS - Auditorium Stage Flooring install begins.
  • CHS - School Store Coiling Door install.
  • CHS - Auditorium Lobby Temp Wall Demo.
  • CHS - Auditorium Lobby Ceiling Tile & Grid install begins.