October Updates
Bond Project - October 3, 2025 Update
Current Activities & Tasks
- CHS – Punch List Repairs in progress.
- CHS – Auditorium Stage Lighting in progress.
- CHS – Auditorium Lobby New Bathroom Masonry Walls install complete.
- CHS – Auditorium Lobby Oval Ceiling Framing in progress.
- CHS – Auditorium Lobby Plumbing in progress.
- CHS – New Weight Room Final Cleaning
Upcoming Activities & Tasks
- CHS – Continue Punch List Repairs.
- CHS – Auditorium Lobby Bathroom Tile install begins.