October Updates

Bond Project - October 10, 2025 Update

CHS - Auditorium Lobby Drywall Install in Progress
CHS - Auditorium Lobby Drywall Install in Progress
CHS - Auditorium Lobby Toilet Room Tile In Progress
CHS - Auditorium Lobby Toilet Room Tile In Progress
CHS - Storage Space Drywall in Progress
CHS - Storage Space Drywall in Progress

Current Activities & Tasks

  • CHS – Punch List Repairs in progress.
  • CHS – Auditorium Stage Lighting in progress.
  • CHS – Auditorium Lobby New Toilet Room Tile & grout Installation in progress.
  • CHS – Auditorium Lobby Oval Ceiling Drywall Installation in progress
  • CHS – Auditorium Lobby Plumbing in progress.

Upcoming Activities & Tasks

  •  CHS – Continue Punch List Repairs.
  • CHS – Auditorium Lobby Thin Brick Installation Begins.
  • CHS – New Gym Wall Pads Install.
  • CHS – New School Store Countertop & Coiling Door Install.