Bond Project - October 24, 2025 Update

CHS - Auditorium Lobby Flooring in Progress
CHS - Auditorium Lobby Flooring in Progress
CHS - Auditorium Stage Flooring in Progress
CHS - Auditorium Stage Flooring in Progress
CHS - New School Store Coiling Door
CHS - New School Store Coiling Door
Campus - New Dog Fence Gate between CMS & CES
Campus - New Dog Fence Gate between CMS & CES

Current Activities & Tasks

  • CHS – Punch List Repairs in progress.
  • CHS – Auditorium Stage Lighting in progress.
  • CHS – Auditorium Lobby Plumbing in progress.
  • CHS – Auditorium Stage Flooring in progress.
  • CHS – Auditorium Audio Visual & Sound in progress. 
  • CHS – Auditorium Lobby Ceiling Tile & Grid in progress. 
  • CHS – New School Store Coiling Door install.

Upcoming Activities & Tasks

  • CHS – Continue Punch List Repairs.
  • CHS – Auditorium Stage Wood Floor Staining begins. 
  • CHS – Auditorium Carpet Install. 
  • CHS – Auditorium New Stage Curtains Install. 
  • CHS – Auditorium Interior Signage Install. 
  • CHS – Auditorium Final Cleaning.