November Updates
Bond Project - November 1, 2025 Update
Current Activities & Tasks
- CHS – Punch List Repairs in progress..
- CHS – Auditorium Stage Wood Flooring Painting.
- CHS – Auditorium New Stage Curtains install.
- CHS – Auditorium Lobby & Auditorium Final Cleaning in progress.
- CHS – Auditorium Interior Signage install.
Upcoming Activities & Tasks
- CHS – Continue Punch List Repairs.
- CHS – Owners & Staff Training on Auditorium Audio Visual and Lighting utilization.
- CHS – Removing miscellaneous remaining items in the Auditorium.
- CHS – New Main Lobby Exterior Front Entrance installation.