Bond Project - September 5, 2025 Update

CHS - Front Exterior Back-Lit Signage
CHS - Front Exterior Back-Lit Signage
CHS - Center Courtyard
CHS - Center Courtyard
CHS - Weight Room Flooring in Progress
CHS - Weight Room Flooring in Progress
CHS - Auditorium Lobby Floor Demolition in Progress
CHS - Auditorium Lobby Floor Demolition in Progress

Current Activities & Tasks

  • CHS – Weight Room Floor Prep in progress.
  • CHS – Punch List Repairs in progress.
  • CHS – Athletics Corridor Flooring in progress.
  • CHS – Athletics Canopy Panels in progress.
  • CHS – New Furniture install in progress.
  • CHS – Auditorium Lobby Floor Demo in progress.

Upcoming Activities & Tasks

  • CHS – Continue Weight Room Flooring prep & install.
  • CHS – Continue Auditorium Lobby Corridor Demo.
  • CHS – Continue Auditorium Corridor Masonry Work
  • CHS – Continue Athletic Area Flooring
  • CHS – Continue Athletics Canopy Metal Panel install.