Bond Project - July 11, 2025 Update

CHS - Athletic Office & Storage in Progress
CHS - Athletic Office & Storage in Progress
CHS - I.T. Offices in Progress
CHS - I.T. Offices in Progress
CHS - Media Center Baffle System in Progress
CHS - Media Center Baffle System in Progress
CHS - Central Administration in Progress
CHS - Central Administration in Progress

Current Activities & Tasks

  • ECC – Interior & Exterior Punch List repair items in progress.
  • CHS – Overhead Mechanical / Electrical Continued.
  • CHS – Masonry work continues in Athletics Area.
  • CHS – New Lighting in Classrooms in progress.
  • CHS – Painting in progress.
  • CHS – 2nd FL Floor Demo & Grinding in progress.
  • CHS – Ceiling Grid & Tile Install in progress.

Upcoming Activities & Tasks

  • CHS – Casework Installation Begins.
  • CHS – Continue Painting.
  • CHS – Continue Overhead Mechanical/Electrical.
  • CHS – Continue Ceiling Grid & Tile Install.
  • CHS – Install Flooring in Central Admin.