May Updates
Bond Project - May 30, 2025 Update
Current Activities & Tasks
- ECC – Site Work Continued
- ECC – Final Cleaning In Progress
- ECC – Punch List In Progress
- CHS – Underground Plumbing Continued
- CHS – Overhead Mechanical / Electrical Continued
Upcoming Activities & Tasks
- ECC – Continue Site Work
- ECC – Exterior Punch List
- ECC – Interior Signage Repairs
- CHS – Inspections
ECC – Early Childhood Center
CHS – Clawson High School
CMS – Clawson Middle School
CES – Clawson Elementary School