July Updates
Bond Project - July 25, 2025 Update
Current Activities & Tasks
- ECC – Interior & Exterior Punch List repair items near complete. (97% complete).
- CHS – Overhead Mechanical / Electrical Continued.
- CHS – Masonry work continues in Athletics Area.
- CHS – Bathroom Tile install in progress.
- CHS – Painting in progress.
- CHS – Ceiling Grid & Tile Install in progress.
- CHS – Auditorium Corridor Demo in progress.
- CHS – Casework & Countertops Install in progress
Upcoming Activities & Tasks
- CHS – Casework & Countertops Install continues.
- CHS – Ceiling Grid & Tile Install continues.
- CHS – Bathroom Tile Install continues.
- CHS – New Flooring Install in Classrooms.
ECC – Early Childhood Center (Old Kenwood ES)
CHS – Clawson High School