July Updates

Bond Project - July 18, 2025 Update

CHS - Corridor & Classroom Lighting in Progress
CHS - Corridor & Classroom Lighting in Progress
CHS - Classroom Casework Install in Progress
CHS - Classroom Casework Install in Progress
CHS - Central Admin Carpet Install in Progress
CHS - Central Admin Carpet Install in Progress
CHS - Auditorium Floor Demolition in Progress
CHS - Auditorium Floor Demolition in Progress

Current Activities & Tasks

  • ECC – Interior & Exterior Punch List repair items near complete. (97% complete).
  • CHS – Overhead Mechanical / Electrical Continued.
  • CHS – Masonry work continues in Athletics Area.
  • CHS – Corridor & Classroom Lighting in progress.
  • CHS – Painting in progress.
  • CHS – Ceiling Grid & Tile Install in progress.
  • CHS – Auditorium Floor Demo in progress.
  • CHS – New Casework Install in progress

Upcoming Activities & Tasks

  • CHS – Casework Install continues.
  • CHS – Continue Overhead Mechanical/Electrical.
  • CHS – Continue Ceiling Grid & Tile Install.
  • CHS – Bathroom Tile Install Begins.

ECC – Early Childhood Center (Old Kenwood ES)

CHS – Clawson High School