August Updates
Bond Project - August 1, 2025 Update
Current Activities & Tasks
- ECC – Interior & Exterior Punch List repair items near complete. (97% complete).
- CHS – New Doors, Frames, & Hardware Install in progress.
- CHS – Bathroom Tile install in progress.
- CHS – Classroom & Corridor Painting in progress.
- CHS – Ceiling Grid & Tile install in progress.
- CHS – Center Courtyard Landscaping in progress.
- CHS – Casework & Countertops Install in progress.
Upcoming Activities & Tasks
- CHS – Casework & Countertops Install continues.
- CHS – Doors, Frames, & Hardware install continues.
- CHS – Bathroom Tile Install continues.
- CHS – Carpet & LVT Flooring install continues.
ECC – Early Childhood Center (Old Kenwood ES)
CHS – Clawson High School