Bond Project - August 1, 2025 Update

CHS - Central Admin. in Progress
CHS - Central Admin. in Progress
CHS - Band Room Carpet Install in Progress
CHS - Band Room Carpet Install in Progress
CHS - Classroom LVT Flooring Install in Progress
CHS - Classroom LVT Flooring Install in Progress
CHS - Corridor Painting in Progress
CHS - Corridor Painting in Progress

Current Activities & Tasks

  • ECC – Interior & Exterior Punch List repair items near complete. (97% complete).
  • CHS – New Doors, Frames, & Hardware Install in progress.
  • CHS – Bathroom Tile install in progress.
  • CHS – Classroom & Corridor Painting in progress.
  • CHS – Ceiling Grid & Tile install in progress.
  • CHS – Center Courtyard Landscaping in progress.
  • CHS – Casework & Countertops Install in progress.

Upcoming Activities & Tasks

  • CHS – Casework & Countertops Install continues.
  • CHS – Doors, Frames, & Hardware install continues.
  • CHS – Bathroom Tile Install continues.
  • CHS – Carpet & LVT Flooring install continues.

ECC – Early Childhood Center (Old Kenwood ES)

CHS – Clawson High School