September Updates
Current Activities & Tasks
- ECC – New Exterior Monument Sign Installation.
- CHS – Punch List Repairs in progress.
- CHS – Auditorium Stage Lighting in progress.
- CHS – Auditorium Lobby New Bathroom Masonry Walls install in progress.
- CHS – Auditorium Lobby Metal Stud Walls install in progress.
- CHS – Auditorium Lobby Plumbing in progress.
- CHS – Weight Room Glass Window install in progress.
September Updates
Current Activities & Tasks
• CHS – Punch List Repairs in progress.
• CHS – Auditorium Stage Lighting in progress.
• CHS – Auditorium Lobby Concrete in fill in progress.
• CHS – Athletic Area Paint Touch Ups in progress.
• CHS – Athletic Area Final Cleaning
September Updates
Current Activities & Tasks
- CHS – Punch List Repairs in progress.
- CHS – Athletics Corridor Flooring in progress.
- CHS – Athletic Corridor Painting in progress.
- CHS – Exterior Athletic Canopy Metal Panels in progress.
- CHS – Auditorium Lobby Bathrooms Plumbing in progress.
- CHS – Auditorium Stage Lighting in progress.
September Updates
Current Activities & Tasks
- CHS – Weight Room Floor Prep in progress.
- CHS – Punch List Repairs in progress.
- CHS – Athletics Corridor Flooring in progress.
- CHS – Athletics Canopy Panels in progress.
- CHS – New Furniture install in progress.
- CHS – Auditorium Lobby Floor Demo in progress.
August Updates
Current Activities & Tasks
- CHS – Corridor Flooring & Stair Treads in progress.
- CHS – Bathroom Partitions & Accessories install in progress.
- CHS – Painting Touch Ups in progress.
- CHS – Center & Front Courtyard Landscaping in progress.
- CHS – New Furniture install in progress.
- CHS – Final Cleaning in progress.