March 15, 2024

3/15/2024

Clawson Public Schools 2021 & 2023 Bond Project  CES - soffit framing at main office addition  CES - tile installation at restrooms CES - demolition of windows at Elementary School CES - installing roof top units  Current Activities & Tasks • CES - soffit framing at main office addition • CES - demolition of windows at Elementary School • CES - installing roof top units • CES - installing fiber network Upcoming Activities & Tasks • CES - casework installation • CES - installation of windows at Elementary School • CES - HVAC duct install at main office addition • CES - flooring installation at classrooms CES - Elementary School CHS – High School