Bond Project - May 9, 2025 Update

CHS - Media Center Demolition in Progress
CHS - Media Center Demolition in Progress
ECC - Motor Skills Room Wall Art in Progress
ECC - Motor Skills Room Wall Art in Progress
ECC - Exterior Playground Demolition in Progress
ECC - Exterior Playground Demolition in Progress
ECC - Last Exterior Pair of Doors Install in Progress
ECC - Last Exterior Pair of Doors Install in Progress

Current Activities & Tasks

  • ECC – Site Work in progress.
  • ECC – Motor Skills Room Wall Art in progress.
  • ECC – Interior Doors & Hardware install in progress.
  • ECC – Playground in progress.
  • CHS – Media Center Demolition in progress.
  • CHS – Athletics Area Demolition in progress.

Upcoming Activities & Tasks

  • ECC – Motor Skills Room Wall Art.
  • ECC – Continue Site Work.
  • ECC – Continue Playground Work.
  • ECC  - Interior Cleaning.
  • ECC – Window Shades Installation.