Bond Project - May 9, 2025 Update
Current Activities & Tasks
- ECC – Site Work in progress.
- ECC – Motor Skills Room Wall Art in progress.
- ECC – Interior Doors & Hardware install in progress.
- ECC – Playground in progress.
- CHS – Media Center Demolition in progress.
- CHS – Athletics Area Demolition in progress.
Upcoming Activities & Tasks
- ECC – Motor Skills Room Wall Art.
- ECC – Continue Site Work.
- ECC – Continue Playground Work.
- ECC - Interior Cleaning.
- ECC – Window Shades Installation.