July Updates

Bond Project - July 4, 2025 Update

ECC - New Handrails & Parking Lot Lines
ECC - New Handrails & Parking Lot Lines
ECC - Zoom Room
ECC - Zoom Room
CHS - Media Center Baffle System in Progress
CHS - Media Center Baffle System in Progress
CHS Central Administration Painting in Progress
CHS Central Administration Painting in Progress

Current Activities & Tasks

  • ECC – Interior & Exterior Punch List repair items in progress.
  • CHS – Overhead Mechanical / Electrical Continued.
  • CHS – Masonry work continues in Athletics Area.
  • CHS – Classrooms & Corridors Flooring Demo in progress.
  •  CHS – Painting in progress.
  • CHS – Flooring Demo & Grinding in progress.
  • CHS – Casework materials arrived & will begin install 7/17.

Upcoming Activities & Tasks

  • CHS – Begin Bathroom Floor Tile Install.
  • CHS – Continue Painting.
  • CHS – Continue Overhead Mechanical/Electrical.
  • CHS – Continue Ceiling Grid & Tile Install.

ECC – Early Childhood Center (Old Kenwood ES)

CHS – Clawson High School